Apron Expansion Project

02 Aug 2022
Demolition of existing CCAD cargo facility, construction of new technology forward cargo and seafood transfer facility, including road realignment for efficient truck access, vehicle parking and aircraft cargo ramp and transitioning apron. Project will promote infrastructure expansion for intermodal transfer of seafood and freight and expanded surface accommodation for business, tourism and other industries with a mobility sector connection to aviation.


Progress Report
The project is proceeding on schedule, with the demolition of all structures located within the project area. A RFB was issued for Phase I of the project, which includes expanding the apron out to West Airport Way and South Airport Way. A contractor was selected and a Notice to Proceed was issued on July 25, 2022. Removal of the North portion of East Airport Way and the entirety of South Airport Way has commenced.